Thursday, November 19, 2015

Sort of Heard Back from the County

After a few months of waiting to hear back from the Major Variance with the County...
       Recap:  After we realized we had more land than we thought, we found 4 tree's that could create a 4 tree treehouse.  We made the decision to start from scratch and re-design.  Only problem was that our tree's are 8 ft from the property line and building setbacks are 15 feet....  We paid and put in our application for the Major Variance

Phew, so we turned in our application for the Major Variance a few months back (proposing our idea of building less than 15 feet from the property line) and we were in limbo for the past few months.  In that time, we have been finishing our design to get ready to send off to the engineer.  I have just begun receiving communication from the county (a few things needed to be changed on the site plan (see below)  Site plan has been updated, and we are now waiting once again....  fingers crossed!