Soothing the Bump in the Road

Shea checks out the tree's, while dad
does some off-roading
Last we talked, the city mentioned the treehouse was too small and we were most likely going to run into city problems.  After talking with the city, we had 2 options

1. Go the Major Variance Route (Pricey and still a big chance it wouldn't go through)
2. Go Directly for the Buiding Permit with 2 buidings on the property

I called the city contact and did a pre-chat and told him we were thinking of possibly seperating the minimum square footage in 2 different structures.  (One above the garage and the other being the treehouse)  I was trying to get a feeler from him, and if this would pose an issue on the project.  He let me know that if we proposed that, we would essentially be proposing for a duplex (because there are 2 seperate structures on 1 lot....) 

I then asked the golden question: What if we have stairs attatching the 2 structures?  It sounds like this idea may be easier to obtain a buidling permit for and so we are on this path.